Type of UnavailabilityUnplanned
Capacity TypeFirm
PointIZT Exit
Technical Capacity (kWh/h)26,255,718
Reason for UnavailabilityEquipment maintenance
Publish Date
(UKT)
VerStatusEvent Start
(UKT)
Event End
(UKT)
Available
(kWh/h)
03-Dec-2018 14:062Inactive19-Nov-2018 13:0003-Dec-2018 15:0017,591,324
Remarks:
19-Nov-2018 11:361Inactive19-Nov-2018 13:0008-Dec-2018 13:0017,591,324
Remarks:
Type of UnavailabilityUnplanned
Capacity TypeFirm
PointIBT Entry
Technical Capacity (kWh/h)26,255,718
Reason for UnavailabilityEquipment maintenance
Publish Date
(UKT)
VerStatusEvent Start
(UKT)
Event End
(UKT)
Available
(kWh/h)
03-Dec-2018 14:062Inactive19-Nov-2018 13:0003-Dec-2018 15:0017,591,324
Remarks:
19-Nov-2018 11:361Inactive19-Nov-2018 13:0008-Dec-2018 13:0017,591,324
Remarks:
Type of UnavailabilityUnplanned
Capacity TypeFirm
PointIBT Entry
Technical Capacity (kWh/h)26,255,718
Reason for UnavailabilityEquipment maintenance
Publish Date
(UKT)
VerStatusEvent Start
(UKT)
Event End
(UKT)
Available
(kWh/h)
23-Feb-2018 13:361Inactive26-Feb-2018 05:0016-Mar-2018 05:0026,255,718
Remarks:Compressor maintenance at IBT. All technical capacity still available
Type of UnavailabilityUnplanned
Capacity TypeFirm
PointIZT Exit
Technical Capacity (kWh/h)26,255,718
Reason for UnavailabilityEquipment maintenance
Publish Date
(UKT)
VerStatusEvent Start
(UKT)
Event End
(UKT)
Available
(kWh/h)
23-Feb-2018 13:361Inactive26-Feb-2018 05:0016-Mar-2018 05:0026,255,718
Remarks:Compressor maintenance at IBT. All technical capacity still available
Type of UnavailabilityUnplanned
Capacity TypeFirm
PointIBT Entry
Technical Capacity (kWh/h)26,255,718
Reason for UnavailabilityContinuance of heater project
Publish Date
(UKT)
VerStatusEvent Start
(UKT)
Event End
(UKT)
Available
(kWh/h)
15-Feb-2018 14:341Inactive19-Feb-2018 05:0022-Feb-2018 05:0016,125,879
Remarks:Works impact Export capacity only
Type of UnavailabilityUnplanned
Capacity TypeFirm
PointIZT Exit
Technical Capacity (kWh/h)26,255,718
Reason for UnavailabilityContinuance of heater project
Publish Date
(UKT)
VerStatusEvent Start
(UKT)
Event End
(UKT)
Available
(kWh/h)
15-Feb-2018 14:341Inactive19-Feb-2018 05:0022-Feb-2018 05:0016,125,879
Remarks:Works impact Export capacity only
Type of UnavailabilityUnplanned
Capacity TypeFirm
PointIZT Entry
Technical Capacity (kWh/h)33,476,006
Reason for UnavailabilityContinuance of heater project
Publish Date
(UKT)
VerStatusEvent Start
(UKT)
Event End
(UKT)
Available
(kWh/h)
15-Feb-2018 14:341Inactive19-Feb-2018 05:0022-Feb-2018 05:0033,476,006
Remarks:Works impact Export capacity only
Type of UnavailabilityUnplanned
Capacity TypeFirm
PointIBT Exit
Technical Capacity (kWh/h)33,476,006
Reason for UnavailabilityContinuance of heater project
Publish Date
(UKT)
VerStatusEvent Start
(UKT)
Event End
(UKT)
Available
(kWh/h)
15-Feb-2018 14:341Inactive19-Feb-2018 05:0022-Feb-2018 05:0033,476,006
Remarks:Works impact Export capacity only
Type of UnavailabilityPlanned
Capacity TypeFirm
PointIBT Entry
Technical Capacity (kWh/h)26,255,718
Reason for UnavailabilityPlanned winter maintenance programme.
Publish Date
(UKT)
VerStatusEvent Start
(UKT)
Event End
(UKT)
Available
(kWh/h)
30-Nov-2017 12:311Inactive30-Nov-2017 11:3007-Dec-2017 11:3026,255,718
Remarks:
Type of UnavailabilityPlanned
Capacity TypeFirm
PointIZT Exit
Technical Capacity (kWh/h)26,255,718
Reason for UnavailabilityPlanned winter maintenance programme.
Cancellation Time30-Nov-2017 12:32
Cancellation Comment.
Publish Date
(UKT)
VerStatusEvent Start
(UKT)
Event End
(UKT)
Available
(kWh/h)
30-Nov-2017 12:311Cancelled30-Nov-2017 11:3007-Dec-2017 11:3026,255,718
Remarks:
Type of UnavailabilityPlanned
Capacity TypeFirm
PointIZT Entry
Technical Capacity (kWh/h)33,476,006
Reason for UnavailabilityPlanned winter maintenance programme.
Cancellation Time30-Nov-2017 12:32
Cancellation Comment.
Publish Date
(UKT)
VerStatusEvent Start
(UKT)
Event End
(UKT)
Available
(kWh/h)
30-Nov-2017 12:311Cancelled30-Nov-2017 11:3007-Dec-2017 11:3033,476,006
Remarks:
Type of UnavailabilityPlanned
Capacity TypeFirm
PointIBT Exit
Technical Capacity (kWh/h)33,476,006
Reason for UnavailabilityPlanned winter maintenance programme.
Cancellation Time30-Nov-2017 12:32
Cancellation Comment.
Publish Date
(UKT)
VerStatusEvent Start
(UKT)
Event End
(UKT)
Available
(kWh/h)
30-Nov-2017 12:311Cancelled30-Nov-2017 11:3007-Dec-2017 11:3033,476,006
Remarks:
Type of UnavailabilityPlanned
Capacity TypeFirm
PointIBT Entry
Technical Capacity (kWh/h)26,255,718
Reason for UnavailabilityEquipment maintenance
Publish Date
(UKT)
VerStatusEvent Start
(UKT)
Event End
(UKT)
Available
(kWh/h)
05-Oct-2017 15:521Inactive08-Jan-2018 05:0023-Jan-2018 05:0026,255,718
Remarks:Compressor
Type of UnavailabilityPlanned
Capacity TypeFirm
PointIZT Exit
Technical Capacity (kWh/h)26,255,718
Reason for UnavailabilityEquipment maintenance
Publish Date
(UKT)
VerStatusEvent Start
(UKT)
Event End
(UKT)
Available
(kWh/h)
05-Oct-2017 15:521Inactive08-Jan-2018 05:0023-Jan-2018 05:0026,255,718
Remarks:Compressor
Type of UnavailabilityUnplanned
Capacity TypeFirm
PointIBT Entry
Technical Capacity (kWh/h)26,255,718
Reason for UnavailabilityEquipment maintenance
Publish Date
(UKT)
VerStatusEvent Start
(UKT)
Event End
(UKT)
Available
(kWh/h)
05-Oct-2017 15:501Inactive30-Oct-2017 05:0001-Nov-2017 05:0026,255,718
Remarks:Compressor
Type of UnavailabilityUnplanned
Capacity TypeFirm
PointIZT Exit
Technical Capacity (kWh/h)26,255,718
Reason for UnavailabilityEquipment maintenance
Publish Date
(UKT)
VerStatusEvent Start
(UKT)
Event End
(UKT)
Available
(kWh/h)
05-Oct-2017 15:501Inactive30-Oct-2017 05:0001-Nov-2017 05:0026,255,718
Remarks:Compressor
Type of UnavailabilityUnplanned
Capacity TypeFirm
PointIBT Entry
Technical Capacity (kWh/h)26,255,718
Reason for UnavailabilityEquipment maintenance
Publish Date
(UKT)
VerStatusEvent Start
(UKT)
Event End
(UKT)
Available
(kWh/h)
05-Oct-2017 15:481Inactive16-Oct-2017 05:0019-Oct-2017 05:0026,255,718
Remarks:Compressor
Type of UnavailabilityUnplanned
Capacity TypeFirm
PointIZT Exit
Technical Capacity (kWh/h)26,255,718
Reason for UnavailabilityEquipment maintenance
Publish Date
(UKT)
VerStatusEvent Start
(UKT)
Event End
(UKT)
Available
(kWh/h)
05-Oct-2017 15:481Inactive16-Oct-2017 05:0019-Oct-2017 05:0026,255,718
Remarks:Compressor
Type of UnavailabilityPlanned
Capacity TypeFirm
PointIBT Entry
Technical Capacity (kWh/h)26,255,715
Reason for UnavailabilityEquipment maintenance
Publish Date
(UKT)
VerStatusEvent Start
(UKT)
Event End
(UKT)
Available
(kWh/h)
03-May-2017 11:023Inactive10-Oct-2016 05:0031-Dec-2017 05:0026,255,715
Remarks:End time extended
14-Dec-2016 15:252Inactive10-Oct-2016 05:0001-Jun-2017 05:0026,255,715
Remarks:Programme of work to upgrade heaters at Zeebrugge
14-Dec-2016 15:221Inactive10-Oct-2016 05:0001-Jun-2017 05:0026,255,715
Remarks:Programme of work to upgrade heaters at Zeenrugge
Type of UnavailabilityPlanned
Capacity TypeFirm
PointIZT Exit
Technical Capacity (kWh/h)26,255,715
Reason for UnavailabilityEquipment maintenance
Publish Date
(UKT)
VerStatusEvent Start
(UKT)
Event End
(UKT)
Available
(kWh/h)
03-May-2017 11:023Inactive10-Oct-2016 05:0031-Dec-2017 05:0026,255,715
Remarks:End time extended
14-Dec-2016 15:252Inactive10-Oct-2016 05:0001-Jun-2017 05:0026,255,715
Remarks:Programme of work to upgrade heaters at Zeebrugge
14-Dec-2016 15:221Inactive10-Oct-2016 05:0001-Jun-2017 05:0026,255,715
Remarks:Programme of work to upgrade heaters at Zeenrugge